Excavation and Stone
|
$60,000
|
|
Building Shell (includes carport and exterior doors & windows)
|
$313,000
|
|
Concrete
|
$50,000
|
|
Architect/Engineer Stamp
|
$7,000
|
|
Electric/Phone/Cable
|
$10,000
|
|
Plumbing
|
$10,000
|
|
Heat/Air Conditioning
|
$50,000
|
|
Insulation
|
$25,000
|
|
All Purpose Room Doors
|
$3,000
|
|
External Lighting
|
$10,000
|
|
Bathrooms
|
$10,000
|
|
Kitchen
|
$25,000
|
|
Flooring/Rugs
|
$35,000
|
|
Rooms (wood, drywall, paint, lights, doors, trim, etc.)
|
$52,000
|
|
Blacktop (2.5 inch binder)
|
$40,000
|
|
Total Cost Estimate
|
$700,000
|
|